Continuing from our previous discussion on 360 Feedback scheduling, we complete the discussion by focussing on the final three elements of a 360 project: 4) Survey Live 5) Managing non respondents 6) Report publication and delivery 4) Survey Live (10 working days) This is simply the time that the survey is available to be completed. There is no doubt that […]

CONTINUE READING

Monday, 10 October 2013

At CR Systems we are often asked the question as to the length of time one should allow to schedule a standard 360 Degree Feedback project. Before answering this, it should be noted that there is a direct link between time and quality of feedback. In this article we are considering primarily the time elements with some reference to how […]